Overview as of October, 2024
- Masonry has begun.
- The air handler has arrived.
Overview as of September, 2024
- Cement slab has been poured and completed.
- Masons will begin mid September.
Overview as of August, 2024
- Footings are poured.
- Slabs are beginning to be poured.
- There is a new sidewalk from the school to the greenhouse.
- The fences around the construction site will be modified to allow access to the greenhouse.
Overview as of July, 2024
- Underground utilities have been installed.
- Excavation is beginning.
- Underground electrical is beginning.
Overview as of June, 2024
- Sewer work is beginning.
- Site work is progressing.
Overview as of May, 2024
- First coordination meeting will be held next week.
- Portables onsite will be moved this month.