Landmark Construction Updates

Overview as of October, 2024

  • Masonry has begun.
  • The air handler has arrived.

Overview as of September, 2024

  • Cement slab has been poured and completed.
  • Masons will begin mid September.

Overview as of August, 2024

  • Footings are poured.
  • Slabs are beginning to be poured.
  • There is a new sidewalk from the school to the greenhouse.
  • The fences around the construction site will be modified to allow access to the greenhouse.

Overview as of July, 2024

  • Underground utilities have been installed.
  • Excavation is beginning.
  • Underground electrical is beginning.

Overview as of June, 2024

  • Sewer work is beginning.
  • Site work is progressing.

Overview as of May, 2024

  • First coordination meeting will be held next week.
  • Portables onsite will be moved this month.