Payson High School

Submitted by ts on
Masonry
Cabinets
Tile work
Roof
Masonry cont
beginning tile
Hallway with no roof
PHS Presentation Board
PHS Rendering 1
PHS Rendering 2
PHS Rendering 3

Overview as of March 2024

  • Masonry is continuing.
  • The B wing (south area) is almost complete.
  • Cabinets are currently being installed.
  • Air handlers have been received.
  • Metal roof decking is going on and being worked on.

Overview as of February 2024

  • Masonry is continuing and will be beginning in the gym and wrestling room.
  • The cell tower equipment is currently being installed. T-Mobile is the vendor.
  • Began paining interior classrooms in two areas.
  • Five air handlers will be received this month.

Overview as of January 2024

  • Masonry is continuing. Currently working in areas B, C, & D. (C&D are the gym area.)
  • Main floor concrete slabs are 100% complete.
  • Floors on the second floor are 35% complete.
  • Roof work is beginning.
    • Trusses and roof decking are being installed in areas A and G with roof membrane to follow.
    • Areas F and G- the roof membrane is installed.
  • T-Mobile is installing equipment on the cell tower.
  • The school is approximately 47% complete.

Overview as of December 2023

  • 90% of the main floor and 25% of the second floor have been poured. 
  • There is structural fill around the entire building to ensure work is possible throughout the winter months.
  • Stadium is 100% complete. 
  • The parking lot between the junior high and high school is complete.
  • The school is approximately 40% complete.