Overview as of September, 2024
- Steel has been installed in the auditorium for the balcony.
- Masonry is continuing in the gym.
- Interior block seal is happening in the corridor.
- All trades are continuing and on track.
- The front parking lot and exterior concrete are beginning.
- The new LDS seminary building is currently under construction.
Overview as of August, 2024
- Masonry in the auditorium is complete.
- The steel decking and masonry in the center commons area is complete.
- Masonry in the gym is continuing.
Overview as of July, 2024
- The high walls in the auditorium have been topped out.
- Structural steel in the commons area is beginning.
- Masonry in the gym and auditorium are continuing.
Overview as of June, 2024
- Cabinetry is beginning to be installed.
- Painting is beginning.
- Masonry in the gym and auditorium is continuing.
Overview as of May, 2024
- Masonry in the auditorium and gym are beginning.
- Roofing is continuing.
- The project is moving along well.
Overview as of April, 2024
- Masonry is going well and is continuing.
- The B wing masonry is complete.
- Metal work is beginning in the B wing.
- Masonry in the kitchen is complete.
- Masonry in the gym is beginning.
Overview as of March, 2024
- Masonry is continuing.
- The B wing (south area) is almost complete.
- Cabinets are currently being installed.
- Air handlers have been received.
- Metal roof decking is going on and being worked on.
Overview as of February, 2024
- Masonry is continuing and will be beginning in the gym and wrestling room.
- The cell tower equipment is currently being installed. T-Mobile is the vendor.
- Began paining interior classrooms in two areas.
- Five air handlers will be received this month.
Overview as of January, 2024
- Masonry is continuing. Currently working in areas B, C, & D. (C&D are the gym area.)
- Main floor concrete slabs are 100% complete.
- Floors on the second floor are 35% complete.
- Roof work is beginning.
- Trusses and roof decking are being installed in areas A and G with roof membrane to follow.
- Areas F and G- the roof membrane is installed.
- T-Mobile is installing equipment on the cell tower.
- The school is approximately 47% complete.
Overview as of December, 2023
- 90% of the main floor and 25% of the second floor have been poured.
- There is structural fill around the entire building to ensure work is possible throughout the winter months.
- Stadium is 100% complete.
- The parking lot between the junior high and high school is complete.
- The school is approximately 40% complete.