Springville High School

Submitted by ts on
Storm Drain
Overall NE
Areas F&G
SHS Presentation Board
SHS Rendering 1
SHS Rendering 2
SHS Rendering 3

Overview as of March 2024

  • The bidding process for Pack #3 is complete and pending approval from the Board.
  • The concrete pad is progressing.
  • Irrigation piping through Bird Park is beginning.
  • Masonry, concrete and electrical are all continuing.
  • Beginning to work with the city on preparing for the roadway on 400 South.
  • Bird Park construction will begin pending Board approval on March 13. SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
    • Fields will remain in use until the season ends and then construction will begin.
    • Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
    • Baseball field: new dugouts, new backstops, and announcer booth upgrade.
  • ***Red Devil Drive will be closed during Spring Break to install irrigation piping.***

Overview as of February 2024

  • Underground site utilities are continuing to be installed.
  • 40% of the concrete slabs have been poured.
  • Bird Park plans are out to bid and construction will be expected to begin in early March.
  • ***Red Devil Drive will be closed during Spring Break to install irrigation piping.***

Overview as of January 2024

  • Beginning masonry.
  • Construction pad is 100% complete.
  • Irrigation piping is 75% complete.
  • Footings and floors are continuing to be poured.
  • Coordination with Springville City on Bird Park plans (Bld Pack #3) are being finalized.
  • The school is approximately 17% complete.

Overview as of December 2023

  • Irrigation piping is underway- 30% complete.
  • Beginning stages of pouring floors. 
  • Bid for Bird Park- baseball and softball fields- will be going out in February.
  • The school is approximately 10% complete.