Overview as of March 2024

  • The bathroom tile in all the bathrooms have been completed.
  • The equipment in the kitchen is currently being installed.
  • Flooring on the first floor is being installed.
  • Concrete around the site is being installed and comping along; walkways, plaza, etc.
  • The two elevators are at the beginning phase of installation.
  • The precast concrete stairs in the following areas are being installed: main stairway, auditorium, commons area, and the gyms.

Overview as of February 2024

  • The gyms are painted and equipment is currently being installed.
  • The subfloor in the gyms are close to being installed.
  • The lighting and partition in the gyms have been installed.
  • Interactive monitors and whiteboards are currently being installed in classrooms.
  • The lockers in the locker rooms are currently being installed.
  • The floors in the locker rooms are complete.
  • Plumbing fixtures are beginning to be installed.
  • Data is being installed throughout the building.
  • The sound system is being installed.
  • The block wall between the school and the neighbors will be completed by mid February.

Overview as of January 2024

  • The auditorium work platform (dance floor) has been removed.
  • Currently beginning to build the stage in the auditorium.
  • Currently working on fireproofing all steel structures.
  • the gym air handlers have arrived and are beginning installation.
  • Beginning footings and foundation for the masonry wall between the school and the neighbors.
  • The gyms are currently being painted.
    • 50% complete
  • The school is approximately 83% complete.

Overview as of December 2023

  • Building is now completely waterproof. All roofs are on.
  • Currently working on the mechanical piping and ductwork in the gyms.
  • Auditorium ceiling work is almost complete.
  • 80% of the classroom flooring is installed.
  • Kitchen is close to completion and ready for equipment.
  • North parking lot is complete.
  • The school is approximately 83% complete.